Jan 2010 to Apr 2013 in 3 contracts. Cost of scope $2.8 million. All 3 of these totalled 6km of 72” diameter pipeline including control valve chambers, diversions, road crossings and jackings. Including all small inch piping and line valve chambers. All of them were built in urban subdivisions.
Phase 5: July 2012 to Nov 2012. Cost of scope $500K. Built right down the middle of Canada Way in Burnaby. It was a 1.5 km 60’’ pipeline. All the work was performed during the night, to minimize the traffic burden.