Metro Vancouver Methane Tank Lining
Dec 2012. Cost of scope $60K. Internal lining of two 14’ diameter methane storage tanks located at Iona waste treatment plant. Extra challenging because of the increased hazard of painting inside a confined space.
Dec 2012. Cost of scope $60K. Internal lining of two 14’ diameter methane storage tanks located at Iona waste treatment plant. Extra challenging because of the increased hazard of painting inside a confined space.
Jan 2010 to Apr 2013 in 3 contracts. Cost of scope $2.8 million. All 3 of these totalled 6km of 72” diameter pipeline including control valve chambers, diversions, road crossings and jackings. Including all small inch piping and line valve chambers. All of them were built in urban subdivisions. Phase 5: July 2012 to Nov…
Nov 2013 to Sept 2014. Cost of scope $600K. This project is 4.5km long 24’’ diameter pipeline. Located just below Hemlock Valley ski resort. Challenging rough terrain with steep grades, and small diameter pipes. We were also contracted to paint full lengths of pipe for this project.
July 2014 to Oct 2015. Cost of scope $3 million. Volcano Creek, McLymont creek and Forrest Kerr, this work started with the Volcano Creek run of river 2km of 60.’’ Upon completion, we went right into McLymont Creek 500m of 10’ pipe. All the fitting, welding, lining, coating and the bifurcations. After the first 2…
Jan 2016 to Dec 2016. Cost of scope $800K. We were called in after the original painting contractor was removed. At first, we were only hired to do the lining, then we were given the remainder of the welding scope to complete the job. All this work was done on T&M basis.
Sept 2014 to Dec 2015. Cost of scope $2.6 million. 2.6 km of 94’’ penstock with a variety of challenges including steep grades, remote location, and with difficult access. Included all welding, lining and coatings and installation of the bifurcation.
June 2016 to Jan 2017. Cost of scope $650K. 1.6 km of 12’ diameter pipe. For this project, we performed the coating and lining work for the project.
May 2014 to Aug 2015. Cost of scope $1.2 million. 80” 4.6km penstock near North end of Harrison Lake. Challenging, mountainous terrain. Some of this line was built on a 50% slope down to the powerhouse.
Feb 2016 to Nov 2016. Cost of scope $1.6 million. Repair and refurbishment of 1500’ of 14’ diameter steel penstock originally constructed in 1926. Fabricated and installed several hundred ½” thick reinforcement plates. Replaced two 50’ long penstock sections, one of which was installed at a 45-degree working angle under the pipe gallery in the…
Sept 2014 to Dec 2015. Cost of scope $1.2 million. 1.1 km of 144’’ butt welded pipeline, including lining and coating. Northeast end of Harrison Lake. The crew consisted of 15 personnel during peak construction.